A Future-Proof Network
EV charge speeds are exploding with rapidly battery technology. Existing charging networks are building for now, not the future.
Our network will be future proof, meaning no upgrade is needed now or in the future in order to charge your car at its maximimum speed, regardless of how many other cars are charging along side you.
Our network will be future proof, meaning no upgrade is needed now or in the future in order to charge your car at its maximimum speed, regardless of how many other cars are charging along side you.
The Great Leap Forward
Chinese battery manufacturers are driving rapid change in the speed of charging. These manufacturers supply their own cars (like BYD and Geely) or sell to other car manufacturers (BMW, Mercedes Benz, Stellantis) like CATL. These batteries will become cheaper through mass production and find their way into EVs as product lines are renewed.
The Writing is on the Wall
Along with battery charge capabilities, vehicle manufacturers are upgrading their electrical architecture from 400V to 800-1000V. Separate to battery capabilities, this creates the capability to charge vehicles more rapidly because it requires lower current (amps) and less heat to charge a vehicle.
While it will take some time for the ultra fast charging batteries to make their way into standard EVs it is clear that as battery costs continue to decline, higher speed charging will be standard function of all EVs - to not do so places vehicle manufacturers at a competitive disadvantage.
It will be necessary to to create a charging network that matches this capability in order to allow full adoption of EVs
We have taken stated vehicle manufacturer targets, technology roadmaps and expected sales by vehicle manufacturer to calculate what the average charge speed of Australian EV fleet will look like over the next decade.
While it will take some time for the ultra fast charging batteries to make their way into standard EVs it is clear that as battery costs continue to decline, higher speed charging will be standard function of all EVs - to not do so places vehicle manufacturers at a competitive disadvantage.
It will be necessary to to create a charging network that matches this capability in order to allow full adoption of EVs
We have taken stated vehicle manufacturer targets, technology roadmaps and expected sales by vehicle manufacturer to calculate what the average charge speed of Australian EV fleet will look like over the next decade.
Depot charging does't make sense
The prevailing assumption in the AEMO ISP is that fleet charging will occur at the depot. From a macro-level this makes sense, however it ignores the fact that local network connections will not be strong enough to support mass-vehicle charging overnight. Fleet vehicles often travel 200-300km per day so would require the ability to charge fully overnight. A medium-sized fleet of 50 vehicles would require 350kW of connection to be fully charged for the next day. This is approximately three times the standard low voltage connection for depots. To enable this connection capacity, the depot would require both a connection upgrade and charging equipment. A reasonable expectation of cost for this is $1m. Commercial fleets often locate near each other and an additional risk is that even an upgrade to 350kW draw would be unachievable without far more significant costs due to other depots also wanting to upgrade.
The ISP also ignores the network tariff structure that would make depot charging cost prohibitive. Network demand charges are calculated as the maximum grid draw that occurs between 3pm and 9pm (roughly). Given the generally low energy consumption of a depot (it is a distribution not a production facility), overnight charging will provide the largest grid draw of the facility, and thereby set the demand charges against that consumption. Assuming a relatively low baseline site demand, a low voltage tariff electricity network charges would exceed $0.50/kWh, with additional energy charges to be levied on top of that. Compared with an ultra-fast charging facility where consumption cost are $0.50/kWh, it would be far cheaper to rely on commercial charging infrastructure than to build. Finally, most depots are rented, not owned. Given the economics of depot charging are area already poor, amortising the cost of charging equipment and network upgrades over a 5-7 year period would make any upgrade an economically irrational decision. Existing Charging Networks
The ISP also ignores the network tariff structure that would make depot charging cost prohibitive. Network demand charges are calculated as the maximum grid draw that occurs between 3pm and 9pm (roughly). Given the generally low energy consumption of a depot (it is a distribution not a production facility), overnight charging will provide the largest grid draw of the facility, and thereby set the demand charges against that consumption. Assuming a relatively low baseline site demand, a low voltage tariff electricity network charges would exceed $0.50/kWh, with additional energy charges to be levied on top of that. Compared with an ultra-fast charging facility where consumption cost are $0.50/kWh, it would be far cheaper to rely on commercial charging infrastructure than to build. Finally, most depots are rented, not owned. Given the economics of depot charging are area already poor, amortising the cost of charging equipment and network upgrades over a 5-7 year period would make any upgrade an economically irrational decision. Existing Charging Networks
How much charging can really occur at home?
Making the explicit assumption that the vast majority of early adopters (due to their income status) occupy detached dwellings, and are more likely to own their own home, any historical BTM charging data cannot be easily extrapolated to the population as a whole.
The economic argument for installing a home charger is not compelling.
Using the standard off-peak rates provided by AGL which average out at roughly $0.25/kWh and an average cost of installation of $2400 (RACV) the payback period is somewhere between 5 and 11 years based on usage and the discount rate used.
Immediately this is problematic for renters, whose average occupancy is less than 2 years. It also makes it a marginal investment for people who have a mortgage on their home, particularly in a high inflation/interest rate environment.
By examining the occupancy status and type of dwellings in Melbourne, Sydney and Brisbane it is possible to estimate the overall likelihood of home charger installation, and therefore the total amount of energy that home charging will provide.
By examining the occupancy status and type of dwellings in Melbourne, Sydney and Brisbane it is possible to estimate the overall likelihood of home charger installation, and therefore the total amount of energy that home charging will provide.
This generates the following likelihood of home charger installation
This analysis is not complete without also considering plug-trickle charging. Again, we have made assumptions on the percentage of households who adopt this charging option, not by creating any net present value analysis, but as a complement to installed home charging equipment. The larger proportion of renters and houses without driveways is a result of roughly 18% of overall housing stock being houses with garages or carports that are rented. An 80% adoption of home charging in those households creates consistency with the overall charging from mortgaged households with garages.
This generates the following use of home trickle charging
To determine the proportion of charging that occurs BTM, broad assumptions have to be made. It is assumed that installed home chargers will provide a greater proportion of energy than trickle charging. At the high end of home charging, wall chargers will deliver 80% of total energy required, and at the low end 50%. Whereas, for trickle charging the high end has been estimated at 50% and the low end 30%. Combining these with the probabilities of home charging generates the following ranges for home charging as a proportion of total EV consumption.